Odoo specification: capturing requirements properly
A good Odoo specification describes your processes rather than individual features, shows for each process what standard Odoo covers and where a customisation is needed, makes open points visible and records every decision with its rationale. Add acceptance criteria that let you check later whether the result is right.
Requirements document and specification
In German-speaking countries, two documents are distinguished:
- Requirements document (Lastenheft): what you as a company need, in your words.
- Specification (Pflichtenheft): how the requirements will be implemented, agreed with the partner doing the implementation.
In Odoo projects the two often blur, because Odoo already does a lot as standard. More important than the name is ending up with a shared understanding that both sides have signed off.
Structure of an Odoo specification
- Goals and framework. Why are you introducing Odoo, what should be better afterwards, what's the deadline?
- People involved. Who decides, who tests, who answers questions in which area?
- Processes. Sales, purchasing, warehouse, production, accounting: each process as it should run in future.
- Comparison with the standard. For each process: what does Odoo cover, what gets configured, what needs a customisation?
- Data and interfaces. Which data will be migrated, which systems does Odoo need to talk to?
- Open points. What hasn't been decided yet, and who clarifies it by when?
- Decisions. What was decided, when and why?
- Acceptance criteria. How do you know a process works?
A requirement, properly captured
| Field | Example |
|---|---|
| Process | Goods receipt |
| Today | Paper delivery note, entered by hand in the evening |
| In future | Scanner entry directly on delivery |
| Odoo standard | Goods receipt and Barcode app available |
| Customisation | Read the best-before date from the supplier's label |
| Open | Does this apply to all suppliers or only to food? |
| Decision | Food only, decided on 12 March 2026 by management |
| Acceptance | A goods receipt with 20 lines is entered in under 10 minutes |
A table like this per requirement is quick to write and saves discussions later, because every decision comes with its rationale.
Standard first
The most common cost driver in Odoo implementations is customisations that weren't needed. For every request, first check whether the standard or an existing module from the Odoo Community Association (OCA) covers the process. It's often worth adjusting a process slightly rather than rebuilding Odoo. Every customisation has to be carried along with every Odoo update.
Common mistakes
- Features instead of processes. "We need a field X" doesn't explain what for. Describe the process, and what's needed will follow.
- Rebuilding the old system. Habits from the legacy system aren't automatically requirements.
- Hiding open points. Unclear things don't become clearer by leaving them out. Write them down and name who will clarify them.
- Making decisions only verbally. After three months nobody remembers why something was built the way it was.
- No acceptance criteria. Without them, every acceptance becomes a negotiation.
Frequently asked questions
How long does an Odoo specification need to be? As short as possible, as detailed as necessary. For an SME, one table per process with the fields from the example above is often enough.
Who writes the specification? Together: you describe your processes and goals, the partner adds what Odoo can do as standard and what needs to be customised. Both sign it off.
Can a specification be changed during the project? Yes, that's normal. What matters is that every change is recorded as a decision with date and rationale.
Sources
Jamotion is a digital Odoo partner for SMEs: Odette asks questions until every requirement is clear and records decisions so they can be traced. The Public Preview starts in January 2027. Join the waiting list